2023-11-24 Lüneburg. Building Management is providing information on the final part of the construction work to renovate the rainwater and wastewater systems:


The final construction phase of the rainwater and wastewater renovation east is planned for the next three weeks, from Monday to Thursday (week 48-50). During the closed renovation using inliner technology, there may be increased noise pollution and partial or full closures of the sanitary facilities and kitchenettes.
The users of the affected buildings will be informed accordingly by additional notices in the entrance areas.

The implementation planning is currently as follows:


Date          Building
27.11.23    C11
28.11.23    C16 & C25
29.11.23    C13 & C25
30.11.23    C10 & C11
04.12.23    Remaining work
05.12.23    C11 & C13
06.12.23    C11 & C25
07.12.23    C11 & C25
11.12.23    C16
12.12.23    C16
13.12.23    C25
14.12.23    C10
Bold entries result in blocking